September 5th, 2019
BURLINGTON, ON
The City of Burlington is making improvements to Lakeshore Road from Nelson Avenue to Locust Street. The City did not return a request for exactly when the work is to begin.
Capital Paving Inc. was awarded the project. The project map, included with this update, shows the planned improvements.
Project Scope and Schedule
Schedule and traffic interruptions Work being done
June – complete • Street lighting replacement
September to mid-October
• Lakeshore Road will stay open for this work. The through lane near the ongoing construction will be closed with the centre turn lane used to keep traffic moving in both directions.
• Asphalt path replacement with concrete path – south boulevard.
• Storm sewer repairs
• Sidewalk repairs – north boulevard
• Curb and gutter repairs
Mid-October to early November
• Lakeshore Road will stay open for this work. The through lane near the ongoing construction will be closed with the centre turn lane used to keep traffic moving in both directions.
• Asphalt milling and paving
• Maintenance hole adjustments
• Lane marking
November • Project Completion