Plains Road work will continue into September - was expected to be complete at the end of August.

notices100x100By Staff

September 6, 2016

BURLINGTON, ON

Construction on Plains Road, between Shadeland Avenue and the QEW, will continue to late September.

Delays: Scot Hamilton explains: “This project, which is part of the Plains Road Functional Design and Implementation Strategy and the Cycling Master Plan, was originally scheduled to finish at the end of August,” said Scott Hamilton, Manager of Design and Construction.

“While the majority of the construction has been completed, a two month delay in rehabilitating the watermain means the final paving will now be finished mid-October. We apologize for the delay and inconvenience the extended construction may cause. We are working to get the project done as soon as possible.”

Plains Road, between Shadeland Avenue and the QEW, remains open to traffic although lane restrictions are in place. Please use caution and obey all signs.

For more information about this project, visit www.burlington.ca/construction or contact Dave Johnson, project manager at 905-335-7600, ext. 7507 or david.johnson@burlington.ca.